What are the last three components removed after final clearance in an asbestos project?

Prepare for the Asbestos Project Monitor Exam with our comprehensive study materials. Use multiple choice questions, in-depth explanations, and helpful hints to boost your exam readiness. Master the skills and knowledge needed to excel!

The last three components removed after final clearance in an asbestos project include the negative air machine, barriers, and decon. This sequence is important for ensuring the safety and containment of any residual asbestos fibers during the project’s final stages.

Negative air machines are critical during an asbestos removal project to maintain negative pressure in the work area, effectively filtering the air and preventing contaminants from escaping into adjacent areas. Once the clearance has been achieved and confirmed, removing these machines is one of the final steps, as they are no longer needed to control airborne asbestos fibers.

Barriers, such as plastic sheeting or other physical barriers, are used to contain asbestos debris and prevent its spread. After clearance, once it is confirmed that the area is safe, these barriers can be taken down to open the space without risking contamination.

Decon, short for decontamination stations or areas, is critical throughout the asbestos project for cleaning personnel and equipment before leaving the regulated area. After clearance, this area can be dismantled since it is no longer necessary to prevent contamination after the air quality has been verified.

In contrast, the other options include elements that may not necessarily be among the last components removed after final clearance, such as personal protective equipment and waste disposal, which can be managed